Boston Children's at Brookline Place | Project Schedule

The project schedule below provides information for significant upcoming work for Boston Children’s at Brookline Place. This schedule is updated regularly.

Brookline Place Redevelopment Project

Brookline Place Redevelopment Project

Look Ahead Schedule

March 29, 2019

Current Phase – 3: Construction of 2 Brookline Place (2BP) and 1 Brookline Place (1BP) addition

Upcoming Activities

Weekend Work: 3/30

General:

  • Dismantle of section of sidewalk overhead protection - south of 1BP at pedestrian crosswalk (Brookline Avenue merge to Washington Street); potential Sunday (3/31) work

1 BP: 

  • Ceramic tile install at new bathrooms

2 BP:

  • Level 9 roof – AVB install and sill prep
  • Mechanical work at penthouse and shafts
  • General cleaning

Monday, 4/1 –Friday, 4/4:

Site Operations:

  • Deliveries ongoing by all trades through gates 1 and 3 – this will result in crane operations throughout the week

Earthwork

1 BP:

  • Loading dock - installation of bollards and concrete encasement; prep sub-grade for future asphalt
  • Site landscaping prep work at north side of garage

Façade/Roof:

1BP:

  • Rooftop permanent rail installation
  • Level 1 brick and granite base installation
  • Northeast and southeast vertical expansion joints (new to existing) to be completed
  • North canopy and vestibule buildout ongoing
  • Exterior finish caulking at building façade

2BP:

  • Rooftop rail installation
  • Low parapet and AVB installation
  • Curtain wall installation to continue
  • Terracotta insulation at south façade to continue

Building Interior / Utilities:

1BP:

  • Toilet partitions install at new bathrooms
  • Final MEP controls and building controls to be connected and tested
  • HVAC controls installation at penthouse is ongoing
  • Light fixture installation to continue
  • Firestopping, final taping and sanding and painting of all walls
  • Ceramic tile at L1-L2 bathrooms

2BP:

  • Moisture mitigation to begin
  • Blocking and interior partitions buildout
  • MEP rough installations on-going at all floors
  • Elevator equipment installation
  • Fire-stopping at mechanical and stair shafts
  • Spray fireproofing in remaining areas

Future Activities:

Earthwork

1 BP:

  • Landscaping and hardscaping at 1BP south along Pearl Street

2BP:

Soil grading at loading dock

  • Catenary light poles
  • Final soils and hardscaping

Façade/Roof:

1BP:

  • Final metal panel penetrations sealed
  • North canopy and vestibule complete
  • Exterior doors/entrances complete

2BP:

  • Terracotta installation to continue
  • Construct loading dock entrance and door
  • Metal panels and louvers at penthouse completed
  • Exterior doors/entrances complete
  • Building is weather tight

Building Interior / Utilities:

1BP:

  • Stairs 4 and 5 rubber flooring, egress signs, and paint
  • Bathroom finishes and partitions
  • Final light fixtures
  • 1 BP addition lobby complete
  • Final cleaning

2BP:

  • Mechanical, electrical, plumbing, sprinkler rough installations on-going
  • Drywall finish and paint
  • Locker room, bike room and bathroom buildout
  • Final MEP controls and building controls to be connected and tested
  • HVAC controls installation at penthouse to be completed

More information about Boston Children’s at Brookline Place can be found at http://www.childrenshospital.org/about-us/expansion-and-renewal/brookline-place, and photos from the site can be found here.

The Brookline Place project team mailing address is: One Brookline Place, Suite 521, Brookline, MA 02445.